Barnstable, Massachusetts

_MG_3660_edited.jpg

A Commitment to Barnstable and the region

Cape Cod and the Islands are leading the way in efforts to decarbonize the New England electricity grid. In 2018, Massachusetts selected Vineyard Wind to build the nation’s first offshore wind project 35 miles south of Barnstable and 14 miles south of Martha’s Vineyard and Nantucket and interconnecting in Hyannis. This project began onshore construction in Barnstable in 2021, and when completed will interconnect in West Barnstable. Both projects interconnect to the New England electricity grid powering over 400,000 homes and businesses.

Vineyard Wind is committed to responsible offshore wind development, environmental protection, and minimizing short-term impacts to Barnstable residents due to in-road utility installation.  The project and the community have benefited from an open and active dialogue for nearly five years.

WATCH

 

OVERVIEW OF WORK IN BARNSTABLE

Construction in Barnstable includes two offshore transmission cables buried beneath the seafloor, buried beneath Covell’s Beach in Centerville, buried beneath public roadways, and connecting to the electricity grid in Independence Park adjacent to existing substation infrastructure. The permitting process began in 2018. State permitting is complete and federal permitting concluded in early 2021, with construction commencing in the town of Barnstable in the middle of that year. View permitting documents View permitting documents here. View onshore work notices here.

VINEYARD WIND IN BARNSTABLE:

Magnetic Field Monitoring at Covell’s beach

In early 2024, Vineyard Wind 1 received a request from the Town of Barnstable to proactively take magnetic field measurements at Covell’s Beach. While no permitting or other requirements exist to conduct magnetic field monitoring at the Town’s request, and as part of Vineyard Wind 1’s longstanding effort to be a good community partner and neighbor to the town, the project agreed to conduct magnetic field measurements at the beach and make the results available to the public. Vineyard Wind 1 has contracted with Gradient to perform the magnetic field readings at Covell’s Beach. Below are the readings that have been taken thus far.

Letter from the State of Massachusetts regarding compliance for VW1 Monitoring

Magnetic Field Readings

  1. May 23, 2024: Baseline readings were taken at various points on the beach and in the parking lot. This testing was done while all Vineyard Wind 1 electrical infrastructure was turned off. Results found very little existing magnetic fields at the beach at any of the locations that is natural or unassociated with the Vineyard Wind 1 infrastructure. Most readings were between 0-1 milligauss (mG), while the highest readings in the parking lot were approximately 2 mG. Video of that testing being performed: https://vimeo.com/949963371

Summary of magnetic field measurement results at Covell’s beach: June 14, 2024

 

Notes: mG=milligauss. NA= not applicable because no measurements made.

(1) There are two mean and maximum results that correspond to the two measurement events for each transect.

 
VW PURPLE-01.png

Host Community Agreement

dreamstime_xxl_72385103.jpg

Host Community Agreement

In 2018, Vineyard Wind and the Town of Barnstable entered into a Host Community Agreement (HCA) to establish a guide for a long-term, cooperative relationship while providing specific benefits, predictability, and revenue for the town of Barnstable for years to come. 

The full HCA can be found here.

Beyond the Host Community Agreement, Barnstable and Vineyard Wind collaborated on the town’s sewer expansion effort, and co-located sewer infrastructure along the cable route, saving the town millions in project costs, minimizing need for future road construction, and helping to address the significant local environmental impact of wastewater and nitrogen loading that degrades the town’s bays, estuaries, and ponds.

Connecting Onshore

dreamstime_xxl_93695231.jpg

Submarine Cables

Safe, Common, Proven Technology

Burying cables is a standard and safe method to protect cables and reduces risk of exposure, damage, fishing gear hangs, and dramatically reduces magnetic field strength. It is much preferred over the older and more disruptive methods of cable laying.

There are currently six submarine cables beneath Nantucket Sound – two connecting power to Nantucket and four to Martha’s Vineyard including one installed most recently in 2015. Two cables, one at Kalmus Beach in Hyannis and one in Harwich, were installed using the same method (Horizontal Directional Drilling) planned for Vineyard Wind cables. While not all submarine cables are buried, it is the safest option.

Two pairs of submarine cables will connect 1600 megawatts of renewable offshore wind energy to land. The cables will be buried within a 35 mile corridor from the turbines to shore. Multiple cables are necessary to transmit the power and ensure reliability.

Each cable is 220 kilovolts AC and will be buried up to 6 feet below the stable seabed using a hydroplow. A hydroplow vehicle travels slowly along the seafloor on two tracks and uses pressurized water jets to temporarily soften the seabed into which the cable sinks and the trench backfills. The physics are similar to standing barefoot on a beach with your feet sinking into the sand as the waves wash over them. The hydroplow ensures a very narrow disruption of the seabed (six-foot corridor) as well as quick seafloor restoration due to the trench backfilling immediately.

 

Submarine Cable

Onshore cable

 

Cable Landfall

Minimizing Impacts, Protecting Beaches and Natural Resources

The offshore cables connect onshore via underground conduit tunneled beneath the beach using a process called Horizontal Directional Drilling (HDD). This process ensures the cables are safely buried deep beneath the shore.

 
  • HDD is a well-established technology used to bury cables throughout the world. In fact, the Cape currently hosts six (6) buried cables that supply power to Nantucket and Martha’s Vineyard. One of these is located at Kalmus Beach in Hyannis and was installed in 2005 using HDD to power Nantucket.

  • The HDD process starts from the beach parking lot, drills a small tunnel in a deep arc beneath the beach and installs a steel tube conduit deep below the beach with no surface disruption. This process results in the safe, protected cable installation up to 30 feet below the beach.

  • All work at the beach parking lot and in Barnstable roads will be done in the off-season, per agreements with the town.

  • Environmental impacts have been extensively studied by multiple local, state and federal agencies. Vineyard Wind must secure over 30 permits from various agencies before work can commence.

  • Because cables are buried there is no electric field. However, all electricity creates a Magnetic Field (MF) and the modeled studies demonstrate that the MF created by these types of cables are comparable to that emitted by everyday household appliances and a fraction of the naturally occurring MF within the earth.

 

Onshore Cables

Connecting to New England’s Electric Grid

 

From the beach parking lot, cables will be buried beneath town roads and encased in concrete. This portion of our project is comparable to installation of other utilities beneath public roadways.  There are hundreds of miles of cable beneath public roadways in dozens of towns in Massachusetts and existing submarine cable connection sites on Cape Cod in Falmouth, Harwich, and Barnstable.

The project will connect to New England’s electric grid via a substation adjacent to an existing substation in Independence Park in Hyannis.

An example of in-road construction.

 

Frequently Asked Questions

dreamstime_xxl_81622944.jpg

Onshore Work Notices

Untitled design (5).png

CONSTRUCTION WORK NOTICES

 

CONTACT

Vineyard Wind offers a variety of ways for Barnstable residents, visitors, and stakeholders to contact us with questions or comments:

Email: info@vineyardwind.com

Call: 508-717-8964

Mail: 69 Beach Rd. Vineyard Haven, MA 02568