INTER-ARRAY CABLES (IACs) INSTALLATION (#114)
Offshore wind mariner update NO. 114
STATUS: Complete
Beginning on or around January 7th and continuing throughout April 2025, cable laying operations for the inter-array cables will be conducted.
The Cable Laying Vessel CONNECTOR will be conducting cable laying operations for the inter-array cables.
The Trenching Support Vessel SYMPHONY will be performing cable trenching, burial works.
The C-PIONEER will be acting as a stationary support vessel, supporting cable pulling activities for the inter-array cables.
The Cable Protection System Stabilization will be conducted by ADHEMAR DE SAINT VENANT.
The WINDSERVE SPARTAN will be supporting crew transfer operations.
The F/V INCENTIVE & F/V SEAFARER will rotate as safety vessel. They will monitor traffic and facilitate safe movement of fishing vessels, recreational craft, or other transiting vessels around the work sites and project vessels.
Standing by on VHF channel 16
LOCATION(S): Inter-array cable locations within lease area OCS-A 0501
VESSELS:
CLV CONNECTOR
Flag: Luxembourg
Length: 515’
MMSI #: 253751000
SYMPHONY
Flag: Luxembourg
Length: 427’
MMSI #: 253830000
C PIONEER
Flag: USA
Length: 260’
MMSI #: 368291370
ADHEMAR DE SAINT VENANT
Flag: Luxembourg
Length: 312’
MMSI #: 253351000
WINDSERVE SPARTAN
Flag: USA
Length: 95’
MMSI #: 368379170
F/V INCENTIVE
Flag: USA
Length: 80'
MMSI #: 367435050
F/V SEAFARER
Flag: USA
Length: 76'
MMSI #: 367179650
VINEYARD WIND
Michael Clayton, Project Manager, Cell: 484-868-3747 • Email: mclayton@vineyardwind.com
Jen Cullen, Fisheries Liaison, Cell: 508-648-4184 • Email: jcullen@vineyardwind.com
VineyardWind.com • info@vineyardwind.com • 508-717-8964
O&M Building on MV 69 Beach Rd. Vineyard Haven, MA 02568